Quantcast

North Birmingham Times

Saturday, May 18, 2024

City of Birmingham Updates Current Street Resurfacing Project

8

Randall L. Woodfin | Randall L. Woodfin Official Website

Randall L. Woodfin | Randall L. Woodfin Official Website

The City of Birmingham continues to upgrade streets in all 9 council districts through a $12.5 million resurfacing project. Mayor Randall L. Woodfin prioritized work to resurface approximately 43 miles of city streets. The status of the work can be reviewed below by council district. 

  • District 1: Street paving is complete. Striping and final actions have not been finalized.
  • District 2: Paving is near complete. An area of Roebuck Springs is on hold due to a Jefferson County Environmental Services Department sewer replacement project.
  • District 3: Work is underway on ramps and sidewalks. Street paving has not yet started.
  • District 4: Work is underway on ramps and sidewalks. Street paving has not yet started.
  • District 5: Work is underway on ramps and sidewalks. Some road milling has begun.
  • District 6: Work is underway on ramps and sidewalks. Street paving has not yet started.
  • District 7: Some street paving is complete. Goss Street is the next work site.
  • District 8: Some street paving is complete. The contractor is finishing Cullman Avenue. Next work sites include Border Street, 16th Street and 15th Street near Pike Road and Graymont area.
  • District 9: Some street paving is complete. Work is currently underway on Brookfield Lane  across Cherry Avenue. Tree Haven Drive and Castleberry Way are the next work sites.
A street by street listing of work can be viewed here.

Original source can be found here

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS